It’s a 120,000 m² industrial logistics and warehousing area with total investment of 300 million RMB, and will be completed in August 2016.[]
The project was put into operation in October 2015, with a total construction area about 80,000 m².[]
With a total building area of 107,000 m2, backfilling works started in August 2014.[]
Covering an area of 100 acres with a total building area of 55,000 m², the project consists of one single-storey warehouse and one double-storey warehouse, and it’s in operation since June 2015.[]
With a total building area of 83,000 m2, the project was started in February 2014 and was completed in November 2014.[]
Changzhou Phase 2 covers an area over 90 acres with a building area of 36,000 m². The construction started in December 2013 while in October 2014 the project was fully in operation.[]
Covering 226 acres and with a building area near 90,000 m², the project started in May 2013 and was put into operation in August 2014.[]
Covering an area of 120 acres with a building area of 46,000 m², GLP Yangzhou Logistics Park Phase 1 was started on November 20, 2012 and put into service on September 28, 2013.[]
It’s the first regional spare-part distribution center customized by BENZ in China. The project was started in September 2012 and completed in May 2014.[]
The phase 1 project covers 60,000 m² with a building area of 33000 m², and it was put into service in October 2012.[]